Pratama, Farrel (2026) Analisis Uji Produktivitas Sumur Geothermal Dengan Menggunakan Metode Lip Pressure Horizontal Discharge Pada Sumur X Lapangan K-Tb. Other thesis, Universitas Islam Riau.
|
Text
skripsi_213210014_watermark.pdf - Published Version Restricted to Registered users only Download (1MB) | Request a copy |
Abstract
Productivity testing activities on geothermal wells are included in one of the stages after drilling. Well X in the K-TB field is a geothermal well that has just completed the drilling process, so it is necessary to conduct well productivity testing to obtain data on well head pressure and fluid flow rate from the well. Well X in the K-TB field is a 2-phase geothermal well with a steam dominance that has just been drilled. The purpose of adding wells to the K-TB field is to increase the electrical power generated by turbines from the fluid produced by the wells. The stage after drilling a geothermal well is to conduct a geothermal well productivity test, which aims to determine the production capacity of geothermal fluids. The problem that will arise if a productivity test is not carried out is that it will be difficult to determine the production capacity (deliverability) of the well, making it impossible to know whether the well is suitable for use as a production well in the long term. One method that can be used in testing the productivity of a geothermal well is the horizontal discharge test method (lip pressure horizontal discharge). In conducting a well productivity test, after obtaining productivity test data in the form of well head pressure and flow rate, the data can be processed to determine the production capacity of the geothermal well (deliverability). The deliverability curve is then used as a reference in determining the potential electricity generated by the well based on the specific steam consumption (SSC) of the turbine. The data used are well head pressure (WHP), steam rate (Q), inlet turbine pressure, pipe pressure drop, maximum discharge pressure (MDP), and flow control valve opening (%). This data was then processed to obtain the deliverability equation variables with a value of � = 0,2126 and C = 10 = 27,96405 with a deliverability curve error percentage with production test data of 0%-1% for the steam rate. Due to the minimum pressure requirement for the turbine of 12 bar, the optimal operating point for the well is at 13,15 bar with an FCV opening of 25%, which will produce a steam rate of 55,78 t/h and an electricity potential of 7,43 MW.
| Item Type: | Thesis (Other) |
|---|---|
| Contributors: | Contribution Contributors NIDN/NIDK Thesis advisor Putra, Dike Fitriansyah 8820423419 |
| Uncontrolled Keywords: | Horizontal Discharge, Deliverability, SSC Turbine, Geothermal, Electrical Potential |
| Subjects: | T Technology > T Technology (General) |
| Divisions: | > Teknik Perminyakan |
| Depositing User: | Erza Pebriani S.Pd |
| Date Deposited: | 23 Nov 2026 07:58 |
| Last Modified: | 23 Nov 2026 07:58 |
| URI: | https://repository.uir.ac.id/id/eprint/34909 |
Actions (login required)
![]() |
View Item |